WINGS OFFICE COMPLEX: Construction UPDATES

Trevi, the appointed piling contractor, finalised the building foundation in November 2013. Cappa and D’alberto, the main contractor, was mobilised to site in the same month and is currently operating ahead of the agreed work schedule. As of November 2014, 30% of the agreed 32 month work programme has been expended with a projected completion date set for August 2015.

Construction is currently at slab level on the 1st floor, however, preparations for the construction of the 2nd floor in both towers is currently underway. The retaining wall, basement and ground floor slabs have been completed.